Progress billing without the spreadsheet

Progress Draw Schedule & Retainage Calculator

Build a schedule of values, enter what was completed previously and this period, and get the retainage and the payment due on the same column model an architect or lender reviews against. Free, no signup, and nothing leaves your browser.

Your schedule is saved in this browser only. Nothing is uploaded.

Application

Only tick this if the contract says so. The reduction is judged on the whole contract, not line by line — a finished line on a job that has barely started does not release retainage. Currently applying 10.0%.

Schedule of values
Description of workC · Scheduled valueD · PreviousE · This periodF · StoredG · Completed%I · To finishJ · RetainageRemove
$0.000.0%$0.00$0.00
$0.000.0%$0.00$0.00
$0.000.0%$0.00$0.00
Totals$0.00$0.00$0.00$0.00$0.000.0%$0.00$0.00
Payment due this period
Contract sum (schedule of values)
$0.00
Total completed and stored to date
$0.00
Less retainage at 10.0%
$0.00
Total earned less retainage
$0.00
Less previous certificates for payment
$0.00
Current payment due
$0.00
Balance to finish, including retainage
$0.00

The retainage total is the sum of the retainage column, not a percentage of the total, so the column adds up to the figure beneath it. On a long schedule those two differ by a few cents, and it is the column a reviewer checks.

The columns, and why they are lettered

A pay application is not reviewed as a total. It is reviewed column by column against the schedule of values agreed at the start of the job, which is why the AIA G703 continuation sheet letters them. A schedule that invents its own columns is one the reviewer cannot check line against line, and that is what gets a draw held.

C — Scheduled value
What the line is worth in the contract. These add to the contract sum.
D — Completed in previous applications
Work already billed and certified before this period.
E — Completed this period
Work put in place since the last application.
F — Materials presently stored
Delivered to site and paid for, not yet installed. Billable on most contracts, and the column most often disputed.
G — Total completed and stored to date
D + E + F. This is the figure percent complete and retainage are both taken from.
I — Balance to finish
C − G. A negative number here means the line is over-billed, which this tool shows rather than hides.
J — Retainage
The percentage withheld from completed work as security until substantial completion. Typically 5% or 10%.

Where the arithmetic goes wrong

Two mistakes account for most disputed draws, and both are arithmetic rather than judgement.

The first is taking retainage on the total instead of summing the column. Round each line and add them, and the figure differs from a percentage of the total by a few cents on a long schedule. That difference is small and it is also the one a reviewer finds first, because the column visibly does not add to the box beneath it. This tool sums the column.

The second is applying a retainage reduction line by line. Many contracts halve retainage once the job passes 50% complete — the job, not a line. Releasing retainage on a finished line while the project is a quarter built bills money the contract does not yet owe, and it is the kind of error that gets an entire application returned.

A worked draw

A $200,000 contract, 10% retainage, with $60,000 billed previously and $40,000 this period.

Application 2 — total completed $100,000 against a $200,000 contract
LineAmount
Contract sum$200,000.00
Total completed and stored to date$100,000.00
Less retainage at 10%−$10,000.00
Less previous certificates−$54,000.00
Current payment due$36,000.00
Balance to finish, including retainage$110,000.00

The previous certificate is $54,000, not $60,000: the earlier application was also net of its own 10% retainage. Subtracting the gross figure understates the payment due by $6,000, and it is the single most common error on a second draw.

What this is not

This calculates a draw. It is not an AIA document, is not a substitute for the G702 and G703 forms where a contract requires those specific forms, and does not carry an architect's certification. Retainage limits, and whether retainage may be held on stored materials at all, are set by contract and by state law and differ considerably. Check your contract.